Milestones of the runway refurbishment

Get the news about the milestones of the runway rehabilitation works at Luxembourg airport.

SEPTEMBER 2021: Completion of night works

Completion of construction works during nightly RWY closure.

September 01 Scaled


AUGUST 2021: Reduced runway operations

Implementation of reduced runway operations, enabling aircraft operations in one end while construction works are ongoing in the other.

August 01


JULY 2021: Reprofiling completed

Reprofiling for 2021 of the runway completed.

July 01


JUNE 2021: Reducing the runway width

Reducing existing runway width of 60 m to 45 m with two time 7.5 m shoulders. Moving 130 lights and painting 14,000 m2 in one night.

20210612 044608 Copy Scaled


MAY 2021: the major asphalt works start

The asphalt works at night started. Placing asphalt and repainting prior to open the runway.

Aerlux 01 26052021 Web %E2%94%Ac%C2%Ae Lcgdp L1210810 1 Copy


APRIL 2021: the preparatory works start

The first runway renovation started. The works are scheduled in periodic night construction and seasons from April to October until the end of 2022.

Image 36


MARCH 2021: A new security check point

To secure a fast and easy access to the construction site and reduce traffic a new security access point has been built.

E121 March